A glimpse into China-Africa technical cooperation at Uganda's hydro power plant
                 Source: Xinhua | 2018-08-25 18:35:44 | Editor: huaxia

Local engineer Andrew Kamagara works at the office of the Karuma Hydro Power Project in the midwestern district of Kiryandongo, Uganda, on Aug. 2, 2018. (XinhuaZhang Gaiping)

by Ronald Ssekandi and Zhang Gaiping

KIRYANDONGO, Uganda, Aug. 25 (Xinhua) -- Deep in the tunnels dug below River Nile in northern Uganda, Chinese engineers together with their Ugandan counterparts assemble turbines that will generate electricity at the country's largest hydro power plant.

In other parts of the tunnels, local workers under close supervision of Chinese technicians weld metals as concrete trucks come in and out of the tunnels, and outside the tunnels, it is equally busy as workers build several structures.

Zheng Zhuqiang, Chinese ambassador to Uganda, said on Thursday that thousands of youths have gained skills as a result of the construction of the Karuma hydro power plant, whose onstruction started in 2013.

"Over 6,000 Ugandans have been employed by the project. Local employees account for 13 percent of managers, 50 percent of technical workers and 87 percent general workers," Zheng said during an inspection tour to the construction site by Ugandan President Yoweri Museveni.

By the end of 2017, more than 150 million U.S. dollars was paid for local procurement of diesel, cement, steel, wood and vehicles, according to Zheng.

The ambassador said when completed, the plant will generate 4 billion kilowatt hours annually and provide more than 200 million dollars in revenue to the government, which is close to 1 percent of the gross domestic product.

Denis Rubangakene, a worker at the construction site, told Xinhua that working under close supervision from his Chinese instructor, he has now gained skills in metal welding.

He said he was employed at the site without any academic qualification.

"I have come to realize that these people do not bother much about certificate and the level of education as long as you can manage to do the work they give you," Rubangakene said.

He said he has now gained experience and can start his own metal welding workshop when the construction project ends.

"For me I am very sure, when I reach Gulu I will open my workshop. The project has given me something to do in the future," he added.

Andrew Kamagara, a local engineer at the site said the construction project has exposed him to other fields that he never thought of joining.

He said although originally he was a water engineer, the Chinese have exposed him to structural engineering, a skill he now enjoys.

"At school we mostly learnt about theory but when we came here, more theory was added but with the practical bit," Kamagara said. "I will be going away with a lot of structural knowledge. I have gained that information and it increased my confidence in structural design."

Workers go about their work at the Karuma Hydro Power Project construction site in Kiryandongo district, Western Uganda, on Aug. 3, 2018. (XinhuaZhang Gaiping)

Meanwhile, villages neighboring the construction site have started developing, according to Severino Opio, local council leader of Karuma village.

He said the locals employed at the site are now buying land and constructing more permanent houses.

He said safe water points have been extended closer to the villages by Sinohydro, the project contractor.

"I used to collect water from very far and that meant I either had to leave my child in the house or carry him with me to fetch the water. But this borehole was built in the community so it helps us reduce the time spent collecting water," Lydia Buteme, a resident of Karuma village said.

At the national level, the 600-MW power plant will be a game changer in the provision of adequate electricity to power the country's economic development.

Economic experts argue that lack of adequate and cheap electricity was pushing up the cost of production in the country and therefore making its products uncompetitive in the east Africa region where power is cheaper in other nations.

Irene Muloni, minister of energy and mineral development, said construction of the power plant will be completed by the end of next year.

"Construction of the power plant is at 80 percent complete and the transmission part is at 42 percent complete," Muloni said, noting that the first two units of the plant each generating 100MW will be completed by the end of this year.

Museveni thanked China for financing the construction of the power plant, noting that it will be important in providing adequate electricity to fast track the economic development of the country.

"I want to thank the Chinese government because we made a contribution from the government of Uganda money, but the bigger money came from a soft loan from China," Museveni said.

Uganda contributed 15 percent as counterpart funding while China Export and Import Bank is providing financing of up to 85 percent. The total cost is 1.4 billion dollars for the generation plant component of the power plant.

Uganda's power generation and installed capacity is estimated at 930 MW, according to government data.

It is estimated that 1,131 MW will be required to meet the national electricity demand by 2020.

When Karuma and the 183-MW Isimba Hydro Power Plant is complete, the 2020 demand would be surpassed. Isimba Power Plant is also financed and constructed by China.

Back to Top Close
Xinhuanet

A glimpse into China-Africa technical cooperation at Uganda's hydro power plant

Source: Xinhua 2018-08-25 18:35:44

Local engineer Andrew Kamagara works at the office of the Karuma Hydro Power Project in the midwestern district of Kiryandongo, Uganda, on Aug. 2, 2018. (XinhuaZhang Gaiping)

by Ronald Ssekandi and Zhang Gaiping

KIRYANDONGO, Uganda, Aug. 25 (Xinhua) -- Deep in the tunnels dug below River Nile in northern Uganda, Chinese engineers together with their Ugandan counterparts assemble turbines that will generate electricity at the country's largest hydro power plant.

In other parts of the tunnels, local workers under close supervision of Chinese technicians weld metals as concrete trucks come in and out of the tunnels, and outside the tunnels, it is equally busy as workers build several structures.

Zheng Zhuqiang, Chinese ambassador to Uganda, said on Thursday that thousands of youths have gained skills as a result of the construction of the Karuma hydro power plant, whose onstruction started in 2013.

"Over 6,000 Ugandans have been employed by the project. Local employees account for 13 percent of managers, 50 percent of technical workers and 87 percent general workers," Zheng said during an inspection tour to the construction site by Ugandan President Yoweri Museveni.

By the end of 2017, more than 150 million U.S. dollars was paid for local procurement of diesel, cement, steel, wood and vehicles, according to Zheng.

The ambassador said when completed, the plant will generate 4 billion kilowatt hours annually and provide more than 200 million dollars in revenue to the government, which is close to 1 percent of the gross domestic product.

Denis Rubangakene, a worker at the construction site, told Xinhua that working under close supervision from his Chinese instructor, he has now gained skills in metal welding.

He said he was employed at the site without any academic qualification.

"I have come to realize that these people do not bother much about certificate and the level of education as long as you can manage to do the work they give you," Rubangakene said.

He said he has now gained experience and can start his own metal welding workshop when the construction project ends.

"For me I am very sure, when I reach Gulu I will open my workshop. The project has given me something to do in the future," he added.

Andrew Kamagara, a local engineer at the site said the construction project has exposed him to other fields that he never thought of joining.

He said although originally he was a water engineer, the Chinese have exposed him to structural engineering, a skill he now enjoys.

"At school we mostly learnt about theory but when we came here, more theory was added but with the practical bit," Kamagara said. "I will be going away with a lot of structural knowledge. I have gained that information and it increased my confidence in structural design."

Workers go about their work at the Karuma Hydro Power Project construction site in Kiryandongo district, Western Uganda, on Aug. 3, 2018. (XinhuaZhang Gaiping)

Meanwhile, villages neighboring the construction site have started developing, according to Severino Opio, local council leader of Karuma village.

He said the locals employed at the site are now buying land and constructing more permanent houses.

He said safe water points have been extended closer to the villages by Sinohydro, the project contractor.

"I used to collect water from very far and that meant I either had to leave my child in the house or carry him with me to fetch the water. But this borehole was built in the community so it helps us reduce the time spent collecting water," Lydia Buteme, a resident of Karuma village said.

At the national level, the 600-MW power plant will be a game changer in the provision of adequate electricity to power the country's economic development.

Economic experts argue that lack of adequate and cheap electricity was pushing up the cost of production in the country and therefore making its products uncompetitive in the east Africa region where power is cheaper in other nations.

Irene Muloni, minister of energy and mineral development, said construction of the power plant will be completed by the end of next year.

"Construction of the power plant is at 80 percent complete and the transmission part is at 42 percent complete," Muloni said, noting that the first two units of the plant each generating 100MW will be completed by the end of this year.

Museveni thanked China for financing the construction of the power plant, noting that it will be important in providing adequate electricity to fast track the economic development of the country.

"I want to thank the Chinese government because we made a contribution from the government of Uganda money, but the bigger money came from a soft loan from China," Museveni said.

Uganda contributed 15 percent as counterpart funding while China Export and Import Bank is providing financing of up to 85 percent. The total cost is 1.4 billion dollars for the generation plant component of the power plant.

Uganda's power generation and installed capacity is estimated at 930 MW, according to government data.

It is estimated that 1,131 MW will be required to meet the national electricity demand by 2020.

When Karuma and the 183-MW Isimba Hydro Power Plant is complete, the 2020 demand would be surpassed. Isimba Power Plant is also financed and constructed by China.

010020070750000000000000011100001374183131
主站蜘蛛池模板: 在线视频手机国产 | 成人在线观看网址 | 中文字幕精品在线 | 91av在线播放 | 日韩在线短视频 | 手机在线永久免费观看av片 | 一区二区电影在线观看 | 久久99国产精品久久99 | 91免费看片黄 | 亚洲一一在线 | 婷婷久操| 美女精品久久久 | 人人玩人人添人人澡97 | 国产午夜麻豆影院在线观看 | 国产精品理论片 | 在线黄色国产 | 精品久久久久久久久久久院品网 | 久久在线精品视频 | 人人看人人草 | 午夜久久久久久久久 | 亚洲黑丝少妇 | 国产精品久免费的黄网站 | 国产精品福利小视频 | 天天躁日日躁狠狠躁av麻豆 | www免费看片com | 中文字幕日韩av | 国产日产精品一区二区三区四区的观看方式 | 在线va视频 | 蜜臀久久99静品久久久久久 | 激情欧美在线观看 | 婷婷av电影 | 免费看污黄网站 | av九九九| 久热久草在线 | 97在线观看免费观看 | 欧美福利网站 | 久久久久久免费 | 九九热久久免费视频 | 一区二区欧美在线观看 | 亚洲欧美日韩精品久久奇米一区 | av网站在线观看播放 | 成年人免费在线观看 | 国产亚洲视频中文字幕视频 | 久久精品99国产国产 | 天天干天天草天天爽 | 久久精品欧美视频 | 人人爽人人爽人人爽人人爽 | 免费亚洲成人 | 国产乱对白刺激视频在线观看女王 | 在线观看视频亚洲 | 欧美a在线免费观看 | 日韩在线第一区 | 成人免费观看视频网站 | 美女视频黄在线观看 | 欧美狠狠操 | 一区二区三区在线看 | 日日夜夜天天久久 | 日本成人免费在线观看 | 亚洲精品女人久久久 | 日本成人免费在线观看 | 99中文在线 | 一区二区久久 | 99精品视频免费观看视频 | 在线视频欧美精品 | 欧美乱码精品一区 | 成人免费视频a | 91入口在线观看 | 日韩专区 在线 | 亚洲综合激情五月 | 成年人视频在线观看免费 | 亚洲色视频 | 天天干天天干天天射 | 国产一区二区在线观看免费 | 一本之道乱码区 | 久久国产影院 | 亚洲精品在线国产 | 99久久久成人国产精品 | 黄色成人在线观看 | 97电影在线看视频 | 99精品视频在线观看免费 | 99久久精品无码一区二区毛片 | 99精品视频免费在线观看 | av一级片在线观看 | 天天做天天爱夜夜爽 | 欧美成人va| 亚洲黄色精品 | 免费瑟瑟网站 | 久久久在线观看 | 97超碰免费在线观看 | 99色资源 | 亚洲黄污 | 毛片永久新网址首页 | 国产视频丨精品|在线观看 国产精品久久久久久久久久久久午夜 | 免费黄色看片 | 在线观看免费高清视频大全追剧 | 久久欧美在线电影 | 91在线观 | 亚洲综合网 | 婷婷国产v亚洲v欧美久久 |